Commentary: East Providence Council has erred in sequestering, overriding vetoes of ARPA funds

By Roberto L. DaSilva
Posted 9/27/23

During my time in office, I have witnessed numerous capital projects go from initial concept and planning, to funding, bidding, permitting, construction and completion. These processes often take …

This item is available in full to subscribers.

Please log in to continue

Log in

Register to post events


If you'd like to post an event to our calendar, you can create a free account by clicking here.

Note that free accounts do not have access to our subscriber-only content.

Day pass subscribers

Are you a day pass subscriber who needs to log in? Click here to continue.


Commentary: East Providence Council has erred in sequestering, overriding vetoes of ARPA funds

Posted

During my time in office, I have witnessed numerous capital projects go from initial concept and planning, to funding, bidding, permitting, construction and completion. These processes often take several years, if not longer, to complete. This has been the process, a successful one, for years. 

Proper planning, engineering and buy-in from multiple parties including buy-in from the Administration and department heads, who will need to execute these plans of action, are crucial to success. 

Going against best practices, the East Providence City Council recently allocated $12.5 million for several projects and sequestered those funds with no input or buy-in from our Administration. In fact our administration voiced strong opposition to locking up these funds and provided reasons and facts as to why doing what they did would jeopardize those funds because these federal funds have timelines in which they need to be spent. 

These federal funds need to be fully obligated by December 2024 and spent by December 2026 or they go back. The state and each of the 39 municipalities are facing the same problem – they all have the same timeline in place and are facing the same challenges. Engineering firms, architects and construction companies as well as supply chain issues have slowed down the process. 

Under my Administration, we have been working on multiple existing Capital Improvement Projects over the last year that have a similar timeline. In many of these instances, the City has already started the process and expended City resources and funds to complete these projects. 

I hope to work with Council President Bob Rodericks, who understands the complexity associated with these projects and who supported many of the vetoes against allocating these funds, as well as the rest of the East Providence City Council to maximize the use of these funds in the best interest of the entire community.

— DaSilva is mayor of the City of East Providence.

2024 by East Bay Media Group

Barrington · Bristol · East Providence · Little Compton · Portsmouth · Tiverton · Warren · Westport
Meet our staff
Jim McGaw

A lifelong Portsmouth resident, Jim graduated from Portsmouth High School in 1982 and earned a journalism degree from the University of Rhode Island in 1986. He's worked two different stints at East Bay Newspapers, for a total of 18 years with the company so far. When not running all over town bringing you the news from Portsmouth, Jim listens to lots and lots and lots of music, watches obscure silent films from the '20s and usually has three books going at once. He also loves to cook crazy New Orleans dishes for his wife of 25 years, Michelle, and their two sons, Jake and Max.